Scheduling Modes
One of the most powerful features of MSP Planner is its professional scheduling engine. Unlike basic Gantt tools that only track dates, MSP Planner understands the mathematical relationship between Duration, Work, and Units.
The Golden Rule of Scheduling:
Work = Duration × Units
By choosing the correct Scheduling Mode, you tell the app which of these three variables is the "fixed" constant and which ones should be automatically recalculated when you make a change.
1. Fixed Duration
"The deadline is non-negotiable."
In this mode, the duration of the task is locked. If you add more resources (increase Units), the app will automatically reduce the amount of Work required from each person to fit the fixed window.
- Use Case: A fixed-length phase (e.g., a 2-week Sprint or a 1-month UAT period).
- Behavior: Changing Units -> Recalculates Work.