Glossary of Terms
To help you get the most out of MSP Planner, we've defined the key professional scheduling terms used throughout the application and documentation.
A
- Actuals: The real amount of work posted in Jira worklogs, used to compare planned effort against actual execution.
- Actuals-Reconciled Resources: System identities (Violet icon) that represent users who have posted time in Jira but haven't been explicitly added to the planning pool.
- Assignment: The link between a task and a resource, including the amount of time (Units) the resource is dedicated to that task.
B
- Baseline: A saved snapshot of a schedule's start and finish dates, used as a point of reference to track project drift.
- Bottom Pane: The resource view where capacity and allocations are managed.
C
- Capacity: The total available working hours of a resource over a specific period, determined by their calendar and max units.
- Critical Path: The longest sequence of dependent tasks that determines the minimum possible project finish date.
- Critical Path Drift: A high-risk scenario where the critical chain shifts from the original baselined tasks to a new, unexpected set of bottlenecks.
D
- Dependency: A logical link between two tasks that defines the order in which they must be performed (e.g., Finish-to-Start).
- Duration: The total elapsed time between the start and finish of a task.
E
- Explicit Synchronization: The "Push/Pull" model that requires a conscious action to move data between the timeline and Jira, serving as a quality and security gate.
F
- Float (Slack): The amount of time a non-critical task can be delayed without impacting the project's overall finish date.
- Fixed Duration: A scheduling mode where the duration is constant, and adding resources reduces the required work per person.
H
- Hybrid Schedule: A schedule containing both Jira-linked tasks and "schedule-only" tasks/milestones.
I
- Identity Preservation: The technology that ensures tasks and resources maintain their IDs when exported to and imported from MS Project.
L
- Lead: A negative offset in a dependency that allows a successor task to start before the predecessor finishes (overlap).
- Lag: A positive offset in a dependency that adds a mandatory delay between tasks (waiting period).
M
- Max Units: The base capacity setting of a resource (e.g., 100% for full-time), used to calculate available hours in the histogram.
- Milestone: A task with zero duration that represents a key project achievement.
- MSPDI: The XML standard used for the lossless exchange of project data between MSP Planner and Microsoft Project.
R
- Reality Gap: The delta between planned effort and actual worklogs, used to identify optimistic estimation or under-performance.
- Round-Trip: The process of exporting a schedule to MS Project, having it edited externally, and importing it back into Jira without losing identity links.
S
- Scheduling Mode: The rule (Fixed Work, Duration, or Units) that defines how the engine recalculates timing when a variable changes.
- SNET (Start No Earlier Than): A semi-flexible constraint that prevents a task from starting before a specific date.
- Split-Pane: The dual-view workspace featuring the Timeline (Top) and Resource View (Bottom).
T
- Text30: The reserved custom field in Microsoft Project used by MSP Planner to store the identity hash for lossless round-tripping.
- Timeline: The professional planning layer where schedules are modeled, calculated, and visualized.
- Triple-Point Analysis: The governance process of comparing the Baseline (the promise), the Planned (the current guess), and the Actuals (the reality).
Z
- Zero-Byte Architecture: A security model (via Atlassian Forge) ensuring that zero bytes of project data are transferred to external third-party servers for processing or storage.