Quick Start Guide
Welcome to MSP Planner for Jira. This guide will get you from a blank slate to your first professional schedule in five strategic steps.
Step 1: Initialize your Workspace
The application starts with a sample schedule loaded to help you explore the features. To start your own project:
- Follow the Quick Tour: If it's your first time, an interactive tour will guide you through the interface. If you've skipped it, you can replay it via the Quick tour button in the toolbar header.
- Locate the Schedules Selector in the toolbar, click the dropdown, and select "Create new schedule".
- Give your schedule a name and associate it with your Jira project.
- Verify Field Mapping: Since every Jira instance is unique, check the Field Management settings to ensure the timeline is mapped to your preferred custom fields for dates and effort.
Step 2: Establish your Reference Baseline
Instead of duplicating data, MSP Planner creates live links to your Jira issues.
- Click Add Tasks in the toolbar.
- Search for your key Jira issues or select a specific Sprint/Release.
- Click Add. Your Jira issues are now linked as Reference Tasks—any metadata pulled from Jira is preserved, but the scheduling logic remains under your professional control.
Step 3: Structure the Project Model
Organize your tasks into a professional hierarchy to enable accurate roll-ups:
- Select a task and use the Indent button to make it a sub-task.
- Create Milestones (tasks with 0 duration) to mark key delivery dates and synchronization points.
Step 4: Define the Scheduling Logic
Create the deterministic logic of your project:
- Establish Dependencies: Click and drag the end of one task bar to the start of another to create a Finish-to-Start link.
- Choose your Mode: By default, tasks use Auto-scheduling (dates shift automatically). For high-level roadmapping or fixed-date commitments, toggle a task to Manual mode to lock its position on the timeline.
Step 5: Optimize Capacity & Commit
Ensure your plan is achievable before communicating it to the team:
- Go to the Resource View (bottom pane) and assign users to your tasks.
- Analyze Load: Look at the Resource Histogram. If you see red bars, you have over-allocated your team. Resolve this by shifting tasks or reallocating resources.
- Synchronize: Once your plan is vetted, use the Synchronize toolbar to "Push" your approved dates and assignments back to Jira.
Congratulations! You have moved from a simple list of tickets to a professional, governed project schedule.
Next Steps
Now that you have the basics, we recommend exploring:
- The Interface Guide to learn the power-user shortcuts.
- The Synchronization Model to master the explicit push/pull boundary.
- Critical Path Analysis to identify your project risks.
- MS Project Round-Tripping to share your plan with stakeholders.