Skip to main content

Multi-Tier Calendars

One of the most common reasons project schedules fail is the "Generic Resource" fallacy—the assumption that every person is available 8 hours a day, 5 days a week, without exception.

MSP Planner solves this by implementing a Multi-Tier Calendar Model. This ensures that your schedule reflects the actual working time of your team.

Calendars

The Three Tiers of Time

The scheduling engine calculates availability by layering three different calendar levels:

1. The Project Calendar (Tier 1)

This is the global working time for the entire project. It defines the standard working days and hours for the project as a whole.

  • Example: A project might be set to a "Standard 40-hour week" or a "Compressed 4-day week."
  • Impact: All tasks in the project default to this calendar unless overridden.

2. The Resource Calendar (Tier 2)

Individual resources often have different working patterns than the project default.

  • Example: A part-time consultant who only works Tuesdays and Thursdays, or a team member in a different time zone.
  • Impact: The schedule automatically shifts task dates to align with the specific resource's availability.

3. Exception Days & Personal Availability (Tier 3)

The most granular level of planning accounts for specific dates where work cannot happen.

  • Holidays: National or corporate holidays that apply to everyone.
  • Personal Availability: Specific dates for vacations, sick leave, or training.
  • Impact: If a resource is on vacation for a week, the scheduling engine automatically pushes their assigned tasks forward, alerting you to potential delays in the critical path.

Managing Calendars in the Workspace

Editing Calendars

You can access and edit calendars through the Resource Calendar Dialog. This allows you to:

  • Define the standard working hours for a specific resource.
  • Add "Exception Days" (holidays or vacations) to a resource's calendar.
  • Import project-file calendars from an MS Project upload.

The Result: Realistic Scheduling

By combining these three tiers, MSP Planner ensures that:

  • No Work on Holidays: Tasks are never scheduled for a Sunday or a national holiday.
  • Accurate Finish Dates: If a critical task is assigned to a resource who is on vacation for two weeks, the project finish date will realistically shift to account for that absence.
  • Factual Capacity: Resource histograms show "Available Hours" based on the actual calendar, not a theoretical maximum.